G & T Construction Ltd is a privately owned Civil Construction company based in Canterbury. The company was formed in 1994 and has grown steadily since, completing a variety of contracts for local Councils and private customers.

Our aim is to deliver the highest standards of workmanship and to maintain excellent working relationships with our customers, engineers and subcontractors. All projects undertaken by G & T Construction are managed by our team of experienced personnel. This includes the design, costing, project delivery and on site supervision of all work undertaken.

Our staff are supported by a modern fleet of construction machinery and equipment with a company policy of minimal reliance on hired plant. This plant is used in house on our own contract work, and is available for hire on a contract basis or hourly terms.

G & T Construction has an excellent record in regard to work place Health and Safety and hold a Gold SiteWise Certificate. We have an ongoing commitment to health and safety training and education within the workplace.  

The company has a practical and thorough Health and Safety Management Plan in place with regular feedback and input from staff to ensure safety issues are addressed and resolved quickly. G & T Construction operate a Quality Management System conforming to AS/NZS ISO 9001:2015 to ensure all work is completed to specification and the required standards are met.

Current Projects

WDC Rakahuri Pumping Station

G & T Construction were engaged by Shayne Higgs to build a 6mtr deep in ground pumping station on the north side of the Ashley river bridge at Rangiora.

A sheet pile cofferdam was installed and a precast concrete wet well constructed within the excavation.

The contract included a below ground valve chamber and an inlet manhole surrounded by a concrete slab, as well as other site works.

The team also installed a 180 HDPE pipe line across the Ashley River slung under the road bridge.


Dominion Salt sea intake

Following the Kaikoura Earthquakes, the intake to the Dominion Salt plant at Grassmere south of Blenheim no longer functioned as designed due to uplift of the sea bed.

G & T Construction were engaged to provide temporary works and cranage support for the installation of a new extended sea intake.

A sheet piled cofferdam was installed to protect the divers during installation of the pipe work and a crane pad was formed to allow for pile installation to secure the new intake pipe to the sea bed.


CWTP Pond Flow Modifications

Flow improvements were needed to help with mixing in the CWTP Oxidation Ponds. G & T Construction built several structures and modified some existing structures to re direct flows. Included were a precast culvert through the Pond 2 peninsula road and permanent sheet piles walls with flow control gated built in at the West end of Pond 2.

The peninsula dividing Pond 2 into two cells was also extended using demolition waste from our Sludge Lagoon contract as well as waste from the demolition of two local schools.